A filler speed, a seamer rating and a completed-pack count describe different things. Begin a canning-line comparison by writing down the unit, format and measurement window attached to every figure. A clear record is more useful than converting an ambiguous listing into an impressive hourly number.
Keep the original unit visible
Copy the seller's figure and unit exactly before doing any arithmetic. CPM may be used inconsistently in machinery descriptions, so confirm whether it means cans, cases or cycles per minute. If a canning listing says BPH, request clarification instead of silently changing bottles to cans.
| Figure supplied | Question before comparison |
|---|---|
| Cans per minute | Measured cans or a rated machine setting? |
| Cans per hour | Which format and operating window? |
| Cases or packs per minute | How many cans in each completed pack? |
| Cycles per minute | How many cans are handled per cycle? |
Use conversion as arithmetic, not performance evidence
Hypothetical example: 60 cans per minute multiplied by 60 equals 3,600 cans per hour while that rate is maintained. This calculation says nothing about stops, rejects, changeovers or the capabilities of any listing. Label it as a conversion and keep it separate from an observed shift total.
Ask for a complete production window
Request the can and end specifications, product, recorded start and finish, stops and acceptable-can count for the same run. Include the downstream count point. A short video may show operation, but without those details it cannot establish the sustained output of a complete line.
Look beyond the filler and seamer
Record the equipment feeding empty cans, supplying ends, inspecting filled cans and preparing the final pack. Ask which modules and conveyors are included. Compare the whole quoted scope before deciding whether an additional machine or integration work will be needed at the destination.
Keep the comparison sheet honest
Use separate columns for seller-stated rating, demonstrated rate and confirmed output with your format. Leave missing observations blank and ask for them. Sidel's line-assessment approach includes measurement of machine speeds, conveyors and line balance; it supports evaluating the connected process rather than relying on one nameplate figure.
Buying checklist
- Original speed and confirmed unit
- Can, end and product specification
- Rated versus observed output identified
- A common run window for stops, rejects and good cans
- Count point identified
- Complete module list and unresolved capacity questions